The “Gum Slough alternative” for Sabal Trail Transmission’s proposed natural gas pipeline corridor through Sumter County is shown running diagonally across the northern half of the county and then along the county line to Lake County.
Start date proposed for pipeline

Developers of the proposed Sabal Trail natural gas pipeline are expecting federal certification for the project late this year or early next year and getting started on construction by May or June of 2016.
Based on plans developed by Sabal Trail Transmission, LLC, the project will result in the installation of a 36-inch, underground pipeline through more than 36 miles of Sumter County. May 1, 2017, is the target date for the pipeline to be in service.